PROJECTS

Sub-Transmission and Distribution Works in Bijbehara Circle
SCHEME: IPDS

AREA COVERED: Anantnag, Bijbehara, Duru Verinag, Kulgam, Qazigund, Mattan, Devsar, Pahalgam, Aishmuqam, Seer Hamdan, Shangus, Achabal, Kokernag, Arwani, Yaripora, Qaimoh, Ashmuji, Mehmoodpora ,Frisal

Project Cost: 46.79

Sub-Transmission and Distribution Works in Budgam Circle
SCHEME: IPDS

AREA COVERED: Budgam, Khan-Sahib , Chadoora ,Magam, Beerwah and Char-i-Sharief

Project Cost: 21.00

Distribution Works in Anantnag Town
SCHEME: RAPDRP-B

AREA COVERED: Anantnag Town

Project Cost: 28.25

Distribution Works in Dooru Town
SCHEME: RAPDRP-B

AREA COVERED: Dooru Town

Project Cost: 4.21

Distribution Works in Kulgam Town
SCHEME: RAPDRP-B

AREA COVERED: Kulgam Town

Project Cost: 5.63

Distribution Works in Handwara Town
SCHEME: RAPDRP-B

AREA COVERED: Handwara

Project Cost: 7.10

Construction of 33/11kV,1x10 MVA Receiving Station at Tral Bala
SCHEME: IPDS

AREA COVERED: District Pulwama

Project Cost: 3.29

Construction of 33/11kV 6.3 MVA Sub Station at Chowgam
SCHEME: PMDP-Rural

AREA COVERED: District Kulgam

Project Cost: 4.00

Construction of 33/11kV 10 MVA Sub Station at Soibugh
SCHEME: PMDP-Rural

AREA COVERED: District Budgam

Project Cost: 3.38

Construction of 33/11kV,1x10 MVA Receiving Station at Verinag
SCHEME: PMDP_Urban

AREA COVERED: District Anantnag

Project Cost: 3.22

Construction of 33/11kV,1x10 MVA Receiving Station at Anchidora Anantnag
SCHEME: IPDS

AREA COVERED: District Anantnag

Project Cost: 3.15

Construction of 33/11kV,1x6.3 MVA Receiving Station Khrew II
SCHEME: PMDP-Urban

AREA COVERED: District Pulwama

Project Cost: 3.22

Construction of 33/11kV 10 MVA Sub Station at Nusso Bandipora
SCHEME: IPDS

AREA COVERED: District Bandipora

Project Cost: 3.85

Creation of 6.3 MVA Receiving Station Ahmadpora Magam
SCHEME: Languishing Scheme

AREA COVERED: Baramulla

Project Cost:

Creation of 10 MVA Receiving Station Gulshanabad Rajpora
SCHEME: Languishing Scheme

AREA COVERED: Pulwama

Project Cost:

Augmentation of Receiving Station Markundal from 2x6.3 MVA to 2x10 MVA
SCHEME: PMDP

AREA COVERED: District Bandipora

Project Cost:

Augmentation of Receiving Station Kurhama from 2x6.3 MVA to 2x10 MVA
SCHEME: PMDP

AREA COVERED: District Ganderbal

Project Cost:

Augmentation of Receiving Station Ajas from 10+6.3 MVA to 2x10 MVA
SCHEME: PMDP

AREA COVERED: District Bandipora

Project Cost:

Augmentation of Receiving Station Wadwan from 10+6.3 MVA to 2x10 MVA
SCHEME: PMDP

AREA COVERED: District Budgam

Project Cost:

Augmentation of Receiving Station Awantipora from 2x10 MVA to 3x10 MVA
SCHEME: KLC

AREA COVERED: Pulwama

Project Cost:

Creation of 10 MVA Receiving Station Hanjoora
SCHEME: DDUGJY

AREA COVERED: budgam

Project Cost:

Creation of 10 MVA Receiving Station Keran
SCHEME: DDUGJY

AREA COVERED: Kupwara

Project Cost:

Creation of 10 MVA Receiving Station Machil
SCHEME: DDUGJY

AREA COVERED: Kupwara

Project Cost:

Creation of 10 MVA Receiving Station Teetwal
SCHEME: DDUGJY

AREA COVERED: Kupwara

Project Cost:

Creation of 6.3 MVA Receiving Station Nagam
SCHEME: Languishing Scheme

AREA COVERED: Kulgam

Project Cost:

Creation of 6.3 MVA Receiving Station Mastpora Kellar
SCHEME: Languishing Scheme + T&D

AREA COVERED: Shopian

Project Cost:

Creation of 6.3 MVA Receiving Station Batagund Tral
SCHEME: Languishing Scheme + T&D

AREA COVERED: Pulwama

Project Cost:

Creation of 6.3 MVA Receiving Station Chanjmulla
SCHEME: Languishing Scheme + T&D

AREA COVERED: Kupwara

Project Cost:

Creation of 6.3 MVA Receiving Station Tujjar Sharif
SCHEME: Languishing Scheme

AREA COVERED: Baramulla

Project Cost:

Creation of 10 MVA Receiving Station IGC Aglar
SCHEME: Deposit Contribution

AREA COVERED: Shopian

Project Cost:

Augumentation of Receiving Station BK Pora from existing Capacity of 2x6.3 MVA to 2x10+6.3 MVA
SCHEME: PMDP

AREA COVERED: Budgam

Project Cost:

Augmentation of receiving Station Khan Sahib from existing Capacity of 6.3+5 MVA to 10+5 MVA
SCHEME: PMDP

AREA COVERED: Budgam

Project Cost:

Augmentation of receiving Station Wussan from existing Capacity of 10 MVA to 10+6.3 MVA
SCHEME: PMDP

AREA COVERED: Ganderbal

Project Cost:

Augmentation of receiving Station Chandoosa from existing Capacity of 5+6.3 MVA to 10+6.3 MVA
SCHEME: PMDP

AREA COVERED: Baramulla

Project Cost:

Augumentation of receiving Station Seelu from existing Capacity of 10 MVA to 2x10 MVA
SCHEME: PMDP

AREA COVERED: Baramulla

Project Cost:

Augmentation of receiving Station Kunzer from existing Capacity of 10+6.3 MVA to 10+6.3 MVA
SCHEME: PMDP

AREA COVERED: Baramulla

Project Cost:

Supervisory Control and Data Acquisition (SCADA)
SCHEME: RAPDRP-A

AREA COVERED: Srinagar Town

Project Cost: 52.30

Smart Metering
SCHEME: Smart Grid

AREA COVERED: Srinagar and Jammu cities

Project Cost: 125.91

Real Time Data Acquisition System (RTDAS)
SCHEME: IPDS

AREA COVERED: 44 Towns(Non Scada RAPDRP Towns and IPDS Towns)

Project Cost: 4.84